Prerequisites
Shaft walls and machine room walls have their materials configured.
Steps
1.) Check the default pit and ceiling material. The default setting for pit and ceilings is Concrete. Definitions are available separately for the machine room and for the shaft.
2.) Select a material and set heights. Choose the material from the predefined lists, then set heights — cross the input boxes with the mouse cursor for a dimension display. Enable Update automatically so newly entered height values update automatically throughout the project.
3.) Apply shaft-group-related settings if needed. When working with shaft groups, pit and ceiling settings can be configured per shaft group.
Result
The pit and ceiling materials and heights are configured, with automatic updates enabled and shaft-group-specific settings available if needed.
Next Step