Step 2 of 17: Load the Landing Door and the Developer Work Area

PL4.2: Load the Developer Work Area in DigiPara Liftdesigner

Written by Alexandra Göttert

Prerequisites

  • A new independent landing door record exists in the DigiPara BIM Library, with its own description and a defined set of selectable door widths.

  • DigiPara Liftdesigner is also open concurrently.

Steps

1.) Load your edited landing door in DigiPara Liftdesigner. Load the landing door you copied and configured in the previous steps.

2.) Load the Developer Work Area. Select the corresponding BIM component in an existing view frame and click Develop this BIM Component. Alongside the Developer Work Area, DigiPara Liftdesigner automatically loads a Developer LOD View sheet as well.

Result

The landing door is open in the Developer Work Area, with its Developer LOD View also loaded, ready for the next steps.

Next Step